EPIC Daily Operations Summary
Date of report(UTC):
2001/09/06 17:16
Author of report:
Gus Emmanuel
Submitted at:
20010909:17:21
This is a no flight day for the aircraft.
NOTES: The Operations Center, after obtaining Mexican Customs documents for the tax on expendibles requests UCAR to transfer the funds via electronic means. UCAR does so by the end of the day.
MISSION PLANS:
- PRIMARY MISSION:
-
- SECONDARY MISSION:
-
TAKE OFF / LANDING TIMES:
-
Plane |
Take-off Times(UTC) |
Landing Times(UTC) |
NSF C-130 |
|
|
NOAA P-3 |
|
|
Pre-flight briefing times(UTC):
- Update times(UTC):
AIRBORNE MISSION SCIENTIST NAMES:
-
NSF C-130 :
-
NOAA P-3 :
-
SHIP OPERATIONS:
-
Ron Brown under way; New Horizon on schedule
- OTHER SPECIAL OPERATIONS:
-
San Cristobal team launching 0000UTC radiosondes daily
No GTS transmission at this time